Project Update:  July 8th, 2019

Approval to proceed was received in June.  We are looking to have the tender package issued to contractors the week of July 8th, 2019.

Looking Forward

Tender Documents Issued to Contractors

  • Once the tender package has been issued, contractors will prepare bids.  Due to the size, the tender package must be issued for a minimum of 30 calendar days.
  • Once bids have been received, they will be opened and reviewed by administration and procurement staff.  The review will consist of determining if the bids are on budget and each one will be ranked.
  • The highest ranked on budget bid will be brought forward to the Board for approval.
  • Once approval has been received, a contract will be issued to complete the construction of the project.

 Construction is planned to occur in the following phases:

Phase 1

  • Renovation of the north wing of the school to accommodate high school students and the new administration area across from the science labs.
  • High school students and staff will be in the south wing of the school while using the existing administration space.
  • Elementary students will continue to use Riverview.
  • Phase 1 is expected to take 4-6 months.

Phase 2

  • Renovation of the south wing of the school to accommodate elementary students will begin.
  • High School students and staff will move into the north wing of the school and begin using the new administration space.
  • Elementary students will continue to use Riverview.
  • Phase 2 is expected to take 4-6 months.

Phase 3

  • Elementary students will move into the newly renovated elementary spaces.
  • Riverview will be demolished to make way for the large gym and childcare construction.
  • Renovation of the existing gym to our new student commons space.
  • Phase 3 is expected to take 8-10 months.